March 15 - 23, 2018: Tree Clearing
2018 Q2: Clearing, Grubbing, Grading, service connections
2018 Q3: Foundations, Start distribution system expansion
2018 Q4: Start process equipment arrival and installation
2019 Q1: Start construction of building
2019 Q4: Estimated project completion and commissioning
Current project timeline for the Burnaby Mountain DEU — Biomass Expansion Project as of March 20, 2018. Dates will be updated regularly as construction permits and approvals are granted by the City of Burnaby.