2018 Q4: Grubbing, grading, service connections and foundations on site; start underground distribution network extension
2019 Q1: Start building construction and installation of major process equipment
2019 Q4: Estimated project completion and commissioning
Current project timeline for the Burnaby Mountain DEU — Biomass Expansion Project as of September 7, 2018. Dates will be updated regularly as construction permits and approvals are granted by the City of Burnaby.