Current Project Timelines as of September 7, 2018

Sep 11, 2018

2018 Q4: Grubbing, grading, service connections and foundations on site; start underground distribution network extension

2019 Q1: Start building construction and installation of major process equipment

2019 Q4: Estimated project completion and commissioning


Current project timeline for the Burnaby Mountain DEU — Biomass Expansion Project as of September 7, 2018. Dates will be updated regularly as construction permits and approvals are granted by the City of Burnaby.